Power Disruptions on Campus
05/04/2017
JSU Capital Planning and Facilities is working with Alabama Power and Acker Electric to address a bad voltage regulator in the university's substation. Single phase power to lights and common electrical outlets is working, however, three phase power needed for heavy equipment such as air conditioning systems is disrupted.
Service to the entire campus is not consistent and can be varied from one building to the next. Our HVAC technicians are inspecting building by building. We have checked with Thyssenkrupp and all of the elevator equipment is functioning except at Ayers Hall. Please call 256-782-5450 with any questions or concerns.